Project Description
CLIENT: Queensland Rail
TIME FRAME: 5 Days
KEY ACHIEVEMENTS:
- Closure Planning interface
- Construction:
- Gen set Foundation installation
- Conduit route and cable installation Power and signalling
- Termination of Generator and standby power systems Equipment
- Brown field Power modifications
- Commissioning:
- Brown field Power supply Modifications cut over
- Test and commission Generator Set to QR specification
- Test run Generator set for 24 Hours.
- On-time asset handover to Operations and Maintenance Representative